Port Hope – Local Planning Appeal Tribunal Provides Oral Order in Penryn Mason Homes Phase 5 Subdivision Matter

In City Hall

On Friday, May 28, 2021, Members of the Local Planning Appeal Tribunal (LPAT) held a Case Management Conference (CMC) virtually via Zoom in regard to the Penryn Mason Homes Phase 5 Subdivision.

At the request of the Solicitors for both sides, the Tribunal member allowed the conversion of the CMC (or pre-hearing) to a settlement hearing for Phase 1 (also referred to as Phase 5A) of the matter. The Planners for both sides provided expert evidence about the planning instruments presented with the Minutes of Settlement.

After the Planners provided their submissions, the LPAT agreed with the Planners that there is good planning rationale for Phase 5A.

The LPAT also verbally confirmed that those who requested to be a party or participant in the hearing did not object to the phased approach presented in the proposed settlement. The LPAT member also confirmed that there is a desire for the parties and participants to be involved with the appeal of Phase two (also referred to as Block 272).

The LPAT will provide a written Order in the coming weeks, which will be posted on the Tribunal and Municipal websites.

“We are pleased the LPAT agreed that the proposed settlement made good planning sense and that the matter has been dealt with expeditiously,” notes Mayor Sanderson, Mayor of the Municipality of Port Hope. “We will await the final written Order, and provide another update on our website, as it becomes available to us.” 

Pete Fisher
Author: Pete Fisher

Has been a photojournalist for over 30-years and have been honoured to win numerous awards for photography and writing over the years. Best selling author for the book Highway of Heroes - True Patriot Love

You may also read!

Golden Plough Lodge Hit With $16,500 Penalty Following Inspection That Identified Multiple Resident Safety Concerns

The Golden Plough Lodge is facing a $16,500 administrative monetary penalty after inspectors identified multiple areas of non-compliance involving

Read More...

Video – Photo Gallery – Parks Canada Undertaking a Major Rehabilitation of Peterborough Canal Dams and Lift Lock

https://www.youtube.com/watch?v=1HKZSrslxDU A major rehabilitation project is underway for the canal dams and the historic Peterborough Lift Lock as Parks Canada

Read More...

Video – Cobourg Marina’s F Dock Being Replaced in $412,000 Project

https://www.youtube.com/watch?v=lSvJaEh6joc A major piece of infrastructure at Cobourg Harbour is being replaced as the Town of Cobourg moves ahead with

Read More...

Mobile Sliding Menu