Ontario Starts Construction on Pickering Nuclear Refurbishment

In Provincial

Refurbishment will create 30,500 good-paying jobs, supporting Canadian sovereignty and strengthening domestic supply chains


As President Trump continues to target Ontario’s economy, the government is acting to secure Ontario’s energy future with the start of construction on the Pickering Nuclear Generating Station refurbishment, Canada’s largest clean energy infrastructure project. As part of its plan to protect Ontario and build a stronger, more self-reliant economy, the project will extend the life of Pickering’s four CANDU reactors by up to 38 years, creating approximately 30,500 jobs annually during construction and 7,500 jobs across Canada over its lifespan. By greenlighting this job-creating project, Ontario is securing decades of reliable, affordable and clean power that Ontario needs to build new homes, attract investment and grow a stronger, more self-reliant economy.

“When the previous government planned to shut down Pickering, our government chose to protect 4,500 jobs and create 30,500 new jobs by doubling down on Canadian workers, technology and energy sovereignty,” said Stephen Lecce, Minister of Energy and Mines. “Today, we are marking a national achievement as we begin work on Canada’s largest clean energy infrastructure project and strengthen our made-in-Ontario nuclear supply chain. The best way Ontario can fight back against President Trump is to build big, which is why we are saying yes to 30,500 jobs, 38 more years of clean power and a stronger Ontario economy. I’m proud that we are not only moving this historic project forward, but awarding contracts that will keep more than 90 per cent of project costs right here in Ontario.”

Following the Ontario government’s approval of Ontario Power Generation’s (OPG) refurbishment plan, the Pickering B units (Units 5 to 8) will be removed from service by the end of September 2026. Once complete, the refurbished station will supply up to 2,200 megawatts (MW) of reliable, affordable power – enough to power 2.2 million homes. Refurbishment will include replacing 1,520 fuel channels, 48 boilers and construction of a 1.5-kilometre deep-water intake. With site construction beginning today, reactor refurbishment work will begin pending final approval from the Canadian Nuclear Safety Commission (CNSC) in January 2027.

Built with Canadian technology and a made-in-Ontario supply chain, the refurbishment is expected to contribute $41.6 billion to Canada’s GDP, with more than 90 per cent of project spending staying in Ontario and Canada. Major contracts awarded to Ontario-based suppliers as part of this work include:

  • Aecon Group Inc. and Candu Energy, an AtkinsRéalis company, for the execution phase of Pickering’s Unit 5 Retube, Feeder and Boiler Replacement (RFBR) project, valued at approximately $1.7 billion.
  • Aecon Group Inc. and Siemens Energy Canada, for Turbine Generator Replacement, including the installation of 14 steam turbine rotors, full stator rewinds, the overhaul of four generators, the delivery of new auxiliary systems and a control and monitoring system valued at $1.3 billion.

“Ontario’s investments in critical infrastructure and our key industries are creating new opportunities for workers across the province,” said Trevor Jones, Minister of Labour, Immigration, Training and Skills Development. “At a time of global economic uncertainty, we are creating good-paying jobs here at home and ensuring our workers have access to the training they need to seize them. By expanding access to apprenticeships and skills training, we are building the workforce Ontario needs to deliver major projects like the Pickering refurbishment and support our continued growth.”

Beyond providing reliable electricity, the Pickering refurbishment will deliver lasting benefits for workers, families and communities across Durham Region and Ontario. The refurbishment will protect highly skilled local jobs and generate more than $17 billion in economic activity across Durham Region and Ontario, creating opportunities for local businesses and communities. Building on Ontario’s world-class nuclear expertise and the lessons learned from the ahead-of-schedule, under-budget Darlington Refurbishment Project, a new 200,000-square-foot Retube, Feeder and Boiler Replacement Training and Mock-up facility will train more than 2,800 skilled trades workers ahead of refurbishment activities, strengthening Ontario’s workforce and made-in-Ontario nuclear supply chain.

“The Pickering Nuclear Refurbishment is a historic investment in Ontario’s clean energy future,” said Peter Bethlenfalvy, MPP for Pickering-Uxbridge. “By creating more than 30,000 jobs, generating billions in economic activity and strengthening our made-in-Ontario nuclear supply chain, this project will deliver generational benefits for workers and families in Pickering and communities across the province.”

As global economic uncertainty and U.S. tariffs place increasing pressure on workers and businesses, our government is moving with speed to strengthen Ontario’s economic sovereignty and energy security while maintaining rigorous regulatory oversight and the highest standards of nuclear safety. The Pickering refurbishment is part of Ontario’s broader plan to expand nuclear generation and strengthen a tariff-proof, recession-proof and almost entirely made-in-Canada industry. Together, Ontario’s nuclear expansion plan will create up to 150,000 jobs and contribute more than $800 billion in GDP to the provincial economy, while providing the reliable, affordable and clean electricity needed to power homes, businesses and future growth.

Refurbishing Ontario’s nuclear fleet is a key pillar of Energy for Generations, our government’s first-ever integrated energy plan to ensure Ontario has the reliable, affordable power needed to support new homes, attract investment and drive economic growth. By extending the life of proven nuclear assets, Ontario is securing decades of electricity at a lower cost than replacing that generation with new sources of power. The government’s integrated approach and record investments in energy infrastructure are providing the certainty needed for municipalities, businesses and industry partners to invest confidently in Ontario’s future. By planning and building today, Ontario is protecting jobs, supporting workers and securing the affordable, reliable energy needed to power economic growth for generations to come.


Quick Facts

  • The Pickering refurbishment builds on Ontario’s proven track record of delivering major nuclear projects, including the Darlington refurbishment delivered nearly five months ahead of schedule and $150 million under budget and the recent Bruce Power Unit 3 Major Component Replacement, completed seven months ahead of schedule and under budget, saving ratepayers $150 million.
  • The Pickering “B” refurbishment is expected to secure a long-term supply of Cobalt-60, a life-saving medical isotope used worldwide in cancer treatments and in the sterilization of medical equipment and food products, while supporting the government’s work to double the number of medical isotopes produced in the province over the next four years.
  • Ontario’s Independent Electricity System Operator (IESO) forecasts that the province’s electricity demand could increase by as much as 90 per cent by 2050, due to population growth, new housing, electrification, advanced manufacturing, and expansion of critical minerals supply chains.
  • In September 2022, the Ontario government announced that OPG would continue to safely operate the “B” units (units 5 to 8) at the Pickering Nuclear Generating Station through September 2026, pending CNSC approval.
  • In October 2024, CNSC authorized Pickering B units to operate until the end of 2026. Further operation of Pickering B units would require a complete refurbishment.
  • In December 2024, OPG completed the Project Initiation Phase of the Pickering refurbishment which included early engineering and design work, as well as securing components that require the longest-lead times.
  • In January 2025, the government approved OPG to proceed with the Project Definition Phase of the Pickering refurbishment that will continue through 2026.
  • In November 2025, the Ontario government approved OPG’s plan to refurbish four CANDU nuclear reactors at the Pickering Nuclear Generating Station.
  • Nuclear power currently provides about 50 per cent of Ontario’s electricity supply and has positioned Ontario as one of the cleanest electricity grids in the world.
  • Ontario’s nuclear industry currently supports around 80,000 good-paying jobs in communities across the province.
Pete Fisher
Author: Pete Fisher

Has been a photojournalist for over 30-years and have been honoured to win numerous awards for photography and writing over the years. Best selling author for the book Highway of Heroes - True Patriot Love

Join Our Newsletter!

Want to keep up to date on news and events in Northumberland? Subscribe to newsletter!

You may also read!

Northumberland OPP – Two People Charged in Drug Trafficking Investigation (Names Released)

Two individuals are facing charges following the execution of a warrant under the Controlled Drugs and Substances Act (CDSA)

Read More...

Durham Region Police – DRPS Officer Charged with Assault (Name Released)

A Durham Regional Police officer has been charged in connection with an assault following an investigation by the Durham

Read More...

Video – Cobourg Police – Person Charged with Obstruct, Trespass, Fail to Comply (Name Released)

https://www.youtube.com/watch?v=SNcKqWVhWTc At approximately noon on October 10, 2026 Cobourg Police were called to a business on King Street West at

Read More...

Mobile Sliding Menu